The masonry restoration began in October 2025, focusing on the wooden and brick façade of Southampton Town Hall, which was originally constructed in 1912. Our team's efforts in restoring the wooden and brick façade aim to maintain its beauty for the local residents.

The project timeline is Fall 2025–Spring 2026
Town Hall will remain open and maintain normal business hours during this period. 

  • Project title: Town Hall Masonry Restoration
  • Project cost: $848,000
  • Project timeline: Fall 2025-Spring 2026
  • Project Contractor: Best Restoration Services, Inc.
  • Project Engineer: L.K. McLean Associates

Specific items of work include:

  • Cleaning existing roof gutters, installing leaf guards, and adding new copper roof leaders
  • Cleaning and repointing existing brick/masonry and stone/brick joints
  • Cleaning existing windows and installing drip edges
  • Installing new lower-level windows
  • Patching existing concrete where necessary
  • Replacing cracked/damaged bricks 
  • Refinishing or removing existing wrought iron balconies
  • Repainting wood trim, fascia and rake boards