Schedule Notes:
General update: Crews will be working on Monday, January 18, 2021.
• Construction preparation:
o On Thursday, January 14, 2021, crews will continue removing the access way along the grassy area south of the Sunrise Highway from Splice Manhole 12.5 near the Speonk-Riverhead Road overpass to Splice Manhole 18.5 at the Old Riverhead Road (Suffolk County Route 31) interchange. The work is planned for daytime hours.
 The work is planned for daytime hours (7 a.m. to 7 p.m.).
 No major traffic issues are anticipated during these activities.
o On Thursday, January 14, 2021, crews will begin stripping topsoil and creating the access way for Splice Manhole 36.5, which is located in the grassy area south of the Sunrise Highway in the area of Newtown Court in Hampton Bays. The work is planned for daytime hours.
 The work is planned for daytime hours (7 a.m. to 7 p.m.).
 No major traffic issues are anticipated during these activities.
o On Friday, January 15, 2021, crews will be setting up traffic control measures and closing the Sunrise Highway rest area in Hampton Bays to install Splice Manhole 35.5. The work is planned for daytime hours.
 The work is planned for daytime hours (7 a.m. to 7 p.m.).
 No major traffic issues are anticipated during these activities.
 During this time, the Sunrise Highway rest area in Hampton Bays will be closed to the public.


o Beginning Monday, January 18, 2021 and extending to Thursday, January 21, 2021, the rest area along Sunrise Highway in Hampton Bays will be closed to all traffic to allow for the installation of Splice Manhole 35.5. Emergency service providers and police please take notice.


• Splice manhole and conduit placement:
o On Monday, December 28, 2020, crews will be installing splice manholes and the new underground electric transmission conduits to interconnect with the existing conduits in the grassy area along the south side of the Sunrise Highway. Crews will use heavy equipment to excavate the soils, lift and place the splice manholes and new conduit, and restore the area The conduit tie-ins are generally two days, and follow after the placement of the splice manhole. The work is planned for daytime hours. For reference, Splice Manhole 22.5 is located on the eastbound onramp of the Quogue-Riverhead Road (Route 104) interchange, with all others located easterly, between Route 104 and Route 24. Splice Manhole 32.5 is located on the eastbound onramp of the Riverhead-Hampton Bays Road (Route 24) with all others located easterly. The schedule of the work for placement is as follows:
 Thursday, January 14, 2021: Conduit tie-ins at 31.5.
 Saturday, January 16, 2021: Conduit tie-ins at 22.5.
 Monday, January 18, 2021: Splice Manhole 35.5 (rest area to be closed to the public during this time).
 Tuesday, January 19, 2021: Splice Manhole 36.5.
 Tuesday, January 19, 2021: Conduit tie-ins at 35.5 (rest area to remain closed to the public during this time).
 Thursday, January 21, 2021: Conduit tie-ins at 36.5.
 The work is planned for daytime hours (7 a.m. to 7 p.m.).
 Work is staged off Sunrise Highway to avoid traffic impacts.
 Rest Area to be closed to the public for work at Manhole 35.5.


• Cable pulling:
o Generally, cable pulling consists of two efforts. First, the cleaning of the new conduits to remove any potential debris resulting in the civil construction process, as well as preparing for the pulling of the cables. Second, the actual cable pulling, which consists of the use of large spools to allow the new electric cables to be pulled through the splice manholes and into the existing and new conduits to the next splice manhole. Large equipment will be staged at both ends of the process to assist with pulling. The work is planned for daytime hours. NOTE: All splice manholes numbered 12.5 and greater are along Sunrise Highway until 37.5.
o The schedule for cable pulling is as follows:
 Thursday, January 14, 2021: Pull cable from 38.5 to 38.5A. NOTE: Splice Manhole 38.5 is located in Canal Road at the Shinnecock Canal Bridge in Hampton Bays, and Splice Manhole 38.5A is located in the eastbound Canal Road onramp to Sunrise Highway. During these activities, full road closures will occur, with temporary detours in place.
 Thursday, January 14, 2021: Swab and clean from 29.5 to 30.5.
 Saturday, January 16, 2021: Pull cable from 26.5 to 27.5.
 Monday, January 18, 2021: Swab and clean from 30.5 to 31.5.
 Tuesday, January 19, 2021: Swab and clean from 31.5 to 32.5.
 Tuesday, January 19, 2021: Pull cable from 27.5 to 28.5.
 Wednesday, January 20, 2021: Swab and clean from 21.5 to 22.5.
 Thursday, January 21, 2021: Swab and clean from 22.5 to 23.5.
 Thursday, January 21, 2021: Pull cable from 21.5 to 22.5.
 The work is planned for daytime hours (7 a.m. to 7 p.m.) except where noted above.
 Work is staged off of Sunrise Highway to avoid traffic impacts.
 At Splice Manholes 38.5 (located in Canal Road near the Shinnecock Canal Bridge in Hampton Bays) and 38.5A (located in the eastbound onramp to the Sunrise Highway from Canal Road in Hampton Bays) single lane closures should be expected with these activities. For 38.5A, a temporary road closure of the onramp will occur, and temporary detours will be in place.
 Signs will be placed to alert motorists.


• Cable Splicing:
o Generally, cable splicing includes a crew working inside of a climate-controlled work trailer positioned directly over the splice manhole to allow for access, and limitations on dust and debris being a part of the process. Crews work continuously for approximately six days to complete each splice. The work is non-obtrusive, and limited to the work trailer. Single lane closures around the splice manhole should be expected during this activity. NOTE: Splice Manholes 12.5 and up are located in the grassy area along the south side of Sunrise Highway, and should not pose any traffic impacts to the public.
o The schedule for cable splicing is as follows:
 Monday, January 11, 2021: The termination of the cable at Canal Substation.
 Monday, January 11, 2021: Splice Manhole 1.5 (located in the LIPA-owned right-of-way).
 Monday, January 18, 2021: Splice Manhole 19.5.
 Monday, January 18, 2021: Splice Manhole 38.5.
 Monday, January 18, 2021: Splice Manhole 24.5.
 The work is continuous for approximately six days.
 No traffic impacts are expected with this activity.


• Work is dependent on the weather.